SECRECY HAS NO LIMITS!

NASA’s James Webb Space Telescope is supposed to be able to see the very building Blocks of all the Universe and then some. But what they have not Released is that they are looking for ET’s Home. A real ET. One that has a Dead Specimen Body of a highly formidable Alien that scared the stuff out of Folks in 1951. And it finally DIED in 1989 when faint word about it was revealed to reverent men who could keep their mouths shut. And it traded vast amounts of knowledge that might take a 100 years to decipher but the Alien traded stuff for information. Food and all. And it Ate Dogs And Cats alive. Really loving Cats the most they’d say. And Up went the Ears on the Ground trying to Locate its Home planet. And Hubble went Up. But No Luck! Pretty Pics but no Home was located for Our Dead Alien. But the search has not Stopped. And Now?

NASA’s James Webb Space Telescope, built to give the world its first glimpse of the universe as it existed when the earliest galaxies formed, was launched by rocket early Saturday from the northeastern coast of South America, opening a new era of astronomy.

https://www.reuters.com/lifestyle/science/nasas-revolutionary-new-space-telescope-due-launch-french-guiana-2021-12-25/

https://en.m.wikipedia.org/wiki/James_Webb_Space_Telescope

NASA’s Goddard Space Flight Center in Greenbelt, Maryland, is leading the management of the observatory project. The project scientist for the James Webb Space Telescope is John C. Mather. Northrop Grumman Aerospace Systems serves as the primary contractor for the development and integration of the observatory. They are responsible for developing and building the spacecraft element, which includes both the satellite bus and sunshield. Ball Aerospace & Technologies has been subcontracted to develop and build the Optical Telescope Element (OTE). Northrop Grumman’s Astro Aerospace business unit has been contracted to build the Deployable Tower Assembly (DTA) which connects the OTE to the spacecraft bus and the Mid Boom Assembly (MBA) which helps to deploy the large sunshields on orbit.[85] Goddard Space Flight Center is also responsible for providing the Integrated Science Instrument Module (ISIM).[47]

Cost growth revealed in spring 2005 led to an August 2005 re-planning.[17] The primary technical outcomes of the re-planning were significant changes in the integration and test plans, a 22-month launch delay (from 2011 to 2013), and elimination of system-level testing for observatory modes at wavelength shorter than 1.7 micrometers. Other major features of the observatory were unchanged. Following the re-planning, the project was independently reviewed in April 2006.

In the 2005 re-plan, the life-cycle cost of the project was estimated at US$4.5 billion. This comprised approximately US$3.5 billion for design, development, launch and commissioning, and approximately US$1.0 billion for ten years of operations.[17] ESA is contributing about €300 million, including the launch.[86] The Canadian Space Agency pledged $39 million Canadian in 2007[87] and in 2012 delivered its contributions in equipment to point the telescope and detect atmospheric conditions on distant planets.[88]

Construction

In January 2007, nine of the ten technology development items in the project successfully passed a Non-Advocate Review.[89] These technologies were deemed sufficiently mature to retire significant risks in the project. The remaining technology development item (the MIRI cryocooler) completed its technology maturation milestone in April 2007. This technology review represented the beginning step in the process that ultimately moved the project into its detailed design phase (Phase C). By May 2007, costs were still on target.[90] In March 2008, the project successfully completed its Preliminary Design Review (PDR). In April 2008, the project passed the Non-Advocate Review. Other passed reviews include the Integrated Science Instrument Module review in March 2009, the Optical Telescope Element review completed in October 2009, and the Sunshield review completed in January 2010.[citation needed]

In April 2010, the telescope passed the technical portion of its Mission Critical Design Review (MCDR). Passing the MCDR signified the integrated observatory can meet all science and engineering requirements for its mission.[91] The MCDR encompassed all previous design reviews. The project schedule underwent review during the months following the MCDR, in a process called the Independent Comprehensive Review Panel, which led to a re-plan of the mission aiming for a 2015 launch, but as late as 2018. By 2010, cost over-runs were impacting other projects, though JWST itself remained on schedule.[92]

By 2011, the JWST project was in the final design and fabrication phase (Phase C). As is typical for a complex design that cannot be changed once launched, there are detailed reviews of every portion of design, construction, and proposed operation. New technological frontiers have been pioneered by the project, and it has passed its design reviews. In the 1990s it was unknown if a telescope so large and low mass was possible.[93]

https://en.m.wikipedia.org/wiki/James_Webb_Space_Telescope

Assembly of the hexagonal segments of the primary mirror, which was done via robotic arm, began in November 2015 and was completed in February 2016.[94] Final construction of the Webb telescope was completed in November 2016, after which extensive testing procedures began.[95] In March 2018, NASA delayed JWST’s launch an additional year to May 2020 after the telescope’s sunshield ripped during a practice deployment and the sunshield’s cables did not sufficiently tighten. In June 2018, NASA delayed the launch by an additional 10 months to March 2021, based on the assessment of the independent review board convened after the failed March 2018 test deployment.[96] The review also found JWST had 344 potential single-point failures.[97] In August 2019, the mechanical integration of the telescope was completed, something that was scheduled to be done 12 years before in 2007. Following this, engineers were working to add a five layer sunshield in place to prevent damage to telescope parts from infrared rays of the Sun.[98]

After construction was completed, JWST underwent final tests at a Northrop Grumman factory in Redondo Beach, California.[99] A ship carrying the telescope left California on 26 September 2021, passed the Panama Canal, and arrived in French Guiana on 12 October 2021.[100]

Cost and schedule issues

On 6 July 2011, the United States House of Representatives’ appropriations committee on Commerce, Justice, and Science moved to cancel the James Webb project by proposing an FY2012 budget that removed US$1.9 billion from NASA’s overall budget, of which roughly one quarter was for JWST.[118][119][120][121] US$3 billion had been spent and 75% of its hardware was in production.[122] This budget proposal was approved by subcommittee vote the following day. The committee charged that the project was “billions of dollars over budget and plagued by poor management”.[118] In response, the American Astronomical Society issued a statement in support of JWST,[123] as did Maryland US Senator Barbara Mikulski.[124] A number of editorials supporting JWST appeared in the international press during 2011 as well.[118][125][126] In November 2011, Congress reversed plans to cancel JWST and instead capped additional funding to complete the project at US$8 billion.[127]

In September 2011, a TOP SECRET Meeting behind Closed Doors took place between the C.I.A. and members of Congress. And it was all about something that was revealed about an Alien Life form that had been keep SECRET by AREA 51. One that had Died in 1989. And was captured in 1951. But this completely Secret Information still remains a Mystery that all will still deny. But what was revealed was this-A formidable Alien might exist that scared those in Charge to find a way to locate where this Alien was from. To FIND their Home! And why? Locate their Homes? TO BLOW THEM UP! And the 1st way of trying to find their Home? That way was through Listening for Signals from Space and attempting to See some indication of Life on another Planet. But a Formidable Foe or Foes? And they got the stuff scared out Of them. And they signed off on lots more money.

Beginning with the U-2 in the 1950s, the base has been the testing ground for a host of top-secret aircraft, including the SR-71 Blackbird, F-117A stealth fighter and B-2 stealth bomber. Some believe the base is also a storage site for alien vehicles, evidence from the “Roswell incident” and extraterrestrial corpses.

Even for those who do not believe, the mystery surrounding the site, situated about 100 miles northwest of Las Vegas, across miles of empty desert speckled with Joshua trees and sagebrush, has been a boon.

One Nevada bicycle event company produces an “X Rides” event that incorporates mountain and road biking near a certain heavily guarded patch of Nevada desert. Las Vegas’ minor league baseball team is called “the 51s.”

Small-town restaurants along State Route 375, officially designated the Extraterrestrial Highway, sell souvenir T-shirts to tourists making their way to the boundary of Area 51, which consists of a no-trespassing sign, a surveillance camera and an armed guard on a hill.

But…there is one Huge dirty little Secret-

AREA 51

YearPlanned
launch
Budget plan
(billion USD)
19972007[93]0.5[93]
19982007[103]1[67]
19992007 to 2008[104]1[67]
20002009[52]1.8[67]
20022010[105]2.5[67]
20032011[106]2.5[67]
200520133[107]
200620144.5[108]
2008, Preliminary Design Review
200820145.1[109]
2010, Critical Design Review
20102015 to 20166.5[110]
201120188.7[111]
201320188.8[112]
20172019[113]8.8
20182020[114]≥8.8
2019March 2021[115]9.66
2021Dec 2021[116]9.70